The work covered by this section consists of preparatory work and operations, including but not limited to those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, for the establishment of offices, buildings, and other facilities necessary for work on the project; removal and disbandment of those personnel, equipment, supplies, incidentals, or other facilities that were established for the prosecution of work on the project; and for all other work and operations which must be performed for costs incurred prior to beginning work on the various items on the project site.
All work covered by this section will be paid for at the contract lump sum price for "Mobilization."
Partial payments for the item of "Mobilization" will be made with the first and second partial pay estimates paid on the contract, and will be made at the rate of 50% lump sum price for "Mobilization" on each of these partial pay estimates, less than the retainage provided for in Article 1094, provided the amount bid for "Mobilization" does not exceed 5 percent of the total amount bid for the contract. Where the amount bid for the item of "Mobilization" exceeds 5 percent of the total amount bid for the contract 2 1/2 percent of the total amount bid will be paid on each of the first two partial pay estimates, and that portion exceeding 5 percent will be paid on the last partial pay estimate. All such payments will be made less the retainage provided for in Article 1094.
As an exception to the above, where the work covered by the contract is limited exclusively to the resurfacing of an existing pavement, payment of the entire lump sum price for the item of "Mobilization," less the retainage provided for in Article 1094, will be made with the first partial pay estimate paid on the contract, provided the amount bid for "Mobilization" does not exceed 5 percent of the total amount bid for the contract. Where the amount bid for the item of "Mobilization" exceeds 5 percent of the total amount bid for the contract, 5 percent of the total amount bid will be paid on the first partial pay estimate, and that portion exceeding 5 percent will be paid on the last partial pay estimate. All such payments will be made less the retainage provided for in Article 1094.
Payment will be made under:
Mobilization Lump-Sum