The Table of Contents for this section is available.
The work covered by this section consists of the construction of a asphalt plant mix base course or surface course composed of a mixture of aggregate, asphalt cement, and mineral filler and other additives when required, properly laid upon a prepared surface, in accordance with these specifications and in conformity with the lines, grades, thickness, and typical sections shown on the plans.
All materials shall meet the requirements of Division 10 shown below:
Fine aggregate Article 1012-1
Mineral filler Article 1012-1
Stone screenings Article 1012-1
Natural sand Article 1012-1
Asphalt cement, Grade AC-20 (See Standard Special Provisions) Article 1020-2
Non-strip additive Article 1020-8
(A) General Requirements:
A single or combination of graded fine aggregates will be required which will produce an acceptable mix. The fine aggregate shall consist of either natural or manufactured materials.
(B) Job Mix Formula:
A job mix formula will be established by the Engineer for the particular materials the Contractor proposes to use in accordance with Article 6103. The job mix formula target values will be established such that when the tolerances (where applicable) are applied, the mixture values will be within the design criteria listed in Table 635.
Additives may be utilized to achieve the required tensile strength ratio, subject to approval by the Engineer.
(C) Requirements for Completed Plant Mix:
The completed plant mix shall conform to the job mix formula within the tolerances shown in Table 635.
When a mix has been tested and has been found to be outside of the design criteria, the Engineer may require the removal from the road of any of this mix which has been placed and which is represented by the test results. All such mix which has been removed shall be replaced with plant mix which is within the job mix formula and allowable tolerances at no cost to the Department.
| No. 4 | |||||||||||
| No. 8 | |||||||||||
| No. 40 | |||||||||||
| No. 80 | |||||||||||
| No. 200 (Dust) | |||||||||||
| AC Content | |||||||||||
| Mix Temperature | |||||||||||
| Number of Blows, each end (4 inch specimen) | |||||||||||
| Stability, Minimum (lbs.) | |||||||||||
| Flow (0.01 in.) | |||||||||||
| Voids in Total Mix, VTM, (%) | |||||||||||
| Voids in Mineral Aggregate, VMA (% Minimum) | |||||||||||
| **Retained Tensile Strength, TSR (% Minimum) | |||||||||||
** ASTM D 4867 "Effect of Moisture on Asphalt Concrete Paving Mixtures" as modified by the Department.
635-4 CONSTRUCTION REQUIREMENTS.
The asphalt plant mix shall be produced, transported to the site, placed, and compacted in accordance with the applicable requirements of Section 610.
Compaction to a specified density will be required where sand asphalt surface course is being used for resurfacing and is required to be applied at a rate of 100 pounds per square yard or greater. The specified density shall be at least 92% of the laboratory density, as determined by the Marshall method of test.
Density control and determination shall be as specified in Article 61011.
The quantity of base course or surface course to be paid for will be the actual number of tons of base course or surface course which has been incorporated into the completed and accepted work. The base course or surface course will be measured by being weighed in trucks on certified platform scales or other certified weighing devices.
The quantity of base course, measured as provided in Article 6355, will be paid for at the contract unit price per ton for "Sand Asphalt Base Course, Type F-1". The quantity of surface course, measured as provided in Article 6355, will be paid for at the contract unit price per ton for "Sand Asphalt Surface Course, Type F-1".
Furnishing asphalt cement for the mix will be paid for as provided in Article 6205 for "Asphalt Cement for Plant Mix".
Furnishing asphalt laboratory facilities will be paid for as provided in Article 6153 for "Field Laboratory Rental, Asphalt Plant Mix".
Furnishing non-strip additive will be paid for as provided in Article 6225 for "Non-Strip Additive".
The above prices and payments will be full compensation for all work covered by this section, including but not limited to producing, weighing, transporting, placing, and compacting the plant mix as specified in Section 610; furnishing the asphalt cement and all other materials for the plant mix; furnishing and applying tack coat as specified in Section 605; furnishing scales; maintaining the base course or surface course until final acceptance of the project; and making any repairs or corrections to the base course or surface course that may become necessary.
Payment will be made under:
Sand Asphalt Base Course, Type F-1 Ton
Sand Asphalt Surface Course, Type F-1 Ton