The work covered by this section consists of furnishing and installing welded steel pipe of the size, thickness, and grade called for on the plans at locations indicated on the plans or designated by the Engineer and to the lines and grades established by the Engineer.
All materials shall meet the requirements of Division 10 shown below:
Welded steel pipe Article 1032-8
Metal pipe culverts, fittings, and all other accessories covered by this section shall be furnished by a supplier who has met the requirements of the Departments Brand Certification program for metal culvert pipes, and is listed on the Departments pre-approved list for suppliers of metal culvert pipe.
Pipe installation shall be in accordance with Section 300 except that where the pipe is to be jacked or bored in place the installation shall be in accordance with the requirements of the special provisions. When jacking or boring, the bore diameter shall be held to a minimum to ensure that there will be no settlement of the pipe.
The quantity of pipe to be paid for will be the actual number of linear feet of pipe which has been incorporated in the completed and accepted work. Measurement will be made by counting the number of joints used and multiplying by the length of the joint. Where partial joints are used, measurement will be made along the longest length of the partial joint to the nearest 0.1 of a foot.
The quantities of pipe, measured as provided in Article 3424, will be paid for at the contact unit prices per linear foot for the various sizes and grades of welded steel pipe shown below.
Payment for foundation conditioning will be made as provided in Subarticle 3009(A).
Payment for providing select material will be made as provided in Subarticle 3009(B).
Payment for providing the bedding material will be made as provided in Subarticle 3009(C).
The above prices and payments will be full compensation for all work covered by this section, including but not limited to furnishing, hauling, and placing all pipe; making all joint connections; all excavation, bedding, and backfill; all jacking or boring; and cleaning out installed pipe.
Payment will be made under:
________Inch Welded Steel Pipe, ________Inch Thick, Grade________
Linear Foot