The work covered by this section consists of all elements of work covered by Section 200, "Clearing and Grubbing"; Section 225, "Roadway Excavation"; Section 230; "Borrow Excavation"; Section 235, "Embankments"; Section 250, "Removal of Existing Pavement"; Section 500, "Fine Grading Subgrade, Shoulders, and Ditches"; and Section 560, "Shoulder Construction"; except that the provisions of the above-referenced sections pertaining to method of measurement, basis of payment, or compensation will not apply unless specific reference is made to such provisions.
The work shall be performed in accordance with the provisions of Sections 200, 225, 230, 235, 250, 500, and 560.
Clearing and grubbing work that is directed by the Engineer to be performed on areas beyond the limits initially staked and/or areas outside the limits of right of way or easements shown in the original plans will be measured by the acre. All measurements will be made horizontally.
All materials which the Contractor has been directed to excavate from the location below the finished graded roadway section will be classified as undercut excavation and will be measured separately in accordance with Article 2257 except for the following.
1. Rock in the bottom of cuts which has been excavated 1 foot or less below the roadbed and ditches.
2. In cut areas, undercut excavation will be limited to excavation removed below the roadbed, removed below the inside slopes of roadway ditches, and removed below the bottom of flat bottom roadway ditches.
All work covered by this section will be paid for at the contract lump-sum price for "Grading" except as otherwise provided below.
Clearing and grubbing work that is directed by the Engineer to be performed on areas outside the limits originally staked or beyond the limits of the right of way or easements shown on the original plans will be paid for at the contract unit price per acre for "Supplementary Clearing and Grubbing". Where the contract does not include this item, a unit price per acre will be established by supplemental agreement.
The quantity of undercut excavation, measured as provided in Article 2263, will be paid for at the contract unit price per cubic yard for "Undercut Excavation". No separate payment will be made for materials utilized in backfilling the undercut areas as payment at the contract unit price per cubic yard for "Undercut Excavation" will be full compensation for furnishing such material. Where the contract does not include an item of "Undercut Excavation", payment for such excavation will be made in accordance with Article 1047.
Payment for material that the Engineer directs to be removed beyond the limits of the original slope stakes will be made in accordance with Article 1043.
Payment for material that the Engineer directs the Contractor to obtain from borrow sources to backfill pipe culverts, box culverts, drainage structures, or structure bents will be made in accordance with Article 1047.
No separate payment will be made for clearing and grubbing or draining borrow sources as such work will be considered incidental to the work covered by this section.
Payment for the work of seeding and mulching all borrow sources will be made at the contract unit prices for the items established in the contract as payment for the work of seeding and mulching.
Partial payments for the item of "Grading" will be made as follows:
The aggregate amount to be paid on each partial payment estimate will be equal to the percentage that the item of "Grading" is complete as estimated by the Engineer.
The above prices and payments will be full compensation for all work covered by this section, including but not limited to all work covered by Sections 200, 225, 230, 235, 250, 500, and 560.
Payment will be made under:
Grading Lump-Sum
Supplementary Clearing and Grubbing Acre
Undercut Excavation Cubic Yard