The Table of Contents for this section is available.
The work covered by this section consists of providing flaggers and flagging equipment in accordance with the plans and specifications.
All materials shall meet the requirements of Division 10 shown below:
Flaggers Article 1089-11
The provisions of Article 1053 will be applicable to work covered by this section.
The Contractor shall provide the services of competent and properly equipped flagger(s) at such locations and for such periods as necessary for the control and protection of vehicular and pedestrian traffic. Flagging methods shall comply with the guidelines in the MUTCD.
All maintenance shall meet the requirements of Article 11054.
The quantity of flaggers (day) to be paid for will be the actual number of days that each flagger is provided during the life of the project. On any calendar day that more than one flagger is used, the quantity to be paid for on that calendar day will be the maximum number of flaggers used at one time in that calendar day.
The quantity of flaggers (hour) to be paid for will be the actual number of hours that each flagger is provided during the life of the project.
Any flagger used for less than one hour will be considered as incidental to the measurement of the quantity of flaggers.
The quantity of flaggers measured as provided in Article 11505 will be paid for at the contract unit price per day for "Flaggers (day)".
The quantity of flaggers measured as provided in Article 11505 will be paid for at the contract unit price per hour for "Flaggers (hour)".
Such price and payment will be full compensation for all work covered by this provision including but not limited to furnishing, relocating, and maintaining the flaggers, hats, vests and STOP/SLOW Paddles and any other incidentals necessary to complete the work.
Payment will be made under:
Flaggers Day
Flaggers Hour