Lateral and Berm Ditches
Lateral drainage ditches and berm ditches (with typical geometry) will be placed
by Roadway in the \DRAINAGE\DRN file.
The DDE criteria has been revised to draw ditches into the plan view
automatically at the same time cross sections are processed.
Meandering Ditches
Natural stream design (meandering ditches) cross sections will be created by
Hydro in a new cross section file (or added to a copy of Roadway's cross sections.)
The COGO chain data will be made available to Roadway for merging into the RDY GPK file.
Berm Ditches
Hydro will provide a COGO profile for berm ditches that do not follow natural downhill contours.
When necessary, Roadway will add the back slope stake of berm ditches to
the DRN file for setting ROW limits.
Roadway CADD support has developed berm ditch criteria to automate these processes. (See Roadway Web site updates of March 21.)
Head/Tail Ditches
Hydro will make sure head and tail ditches are drawn to scale and cut cross sections when necessary.
|