This is a new report that shows the estimated amounts that should have been paid to each subcontractor on a contract to date. This information is based on the estimate payments paid to the Prime Contractor on those line items and the Subcontractor percentage for those line items. It can be used to verify pending Disadvantaged Business Enterprise (DBE) payments on the DBE Payment Tracking web site.
The calculation used to determine the Estimated Amount Paid to Sub is the following:
where Est qty is the Estimate Line Item Total Quantity
Bid Qty is the Contract Plan Quantity
Cert Percent is the Subcontract Line Item Certification Percent
Goals Amount is the Subcontracted qty * Goals Unit Price
If the Bid qty = 1000
Est qty = 100
Subcontracted qty = 1000
Goals unit price = $4.00
Cert percent = 100%
then the Estimated Amount Paid to Sub is 100/1000 * 1 * (1000 * 4.00) = $400