Contract Progress Report
Version 6.1 Changes
- The report has been corrected to display the current contractor on defaulted contracts.
Version 6.0.1 Changes
- Corrected the functioning of the Progress Filter's "Either" criteria.
Version 6.0 Changes
- The report has been modified to prevent periodic application termination when scrolling through the Contract Progress Report.
NEW for Version 5.9
- This new report provides information regarding the actual progression of work for a given Contract versus the Contractor's planned progress submitted on the Progress Schedule.
- The data displayed is for the most recent estimate in the following statuses:
- Paid
- Processed
- Pending CCU Approval
- The fields displayed in the Article108-8 Progress Information box are defined as follows:
- Percent Complete by Progress Chart: Progress Schedule Percent from Review Estimates or Review Contract Details Status tab.
- Actual Percent Complete: Percent Complete from Review Estimates or Completion Percent from Review Contract Details Status tab.
- Percent Overrun/Underrun: % Overrun/Underrun to date from Review Estimates or % Overrun / Underrun from Review Contract Details Status tab.
- Percent Ahead/Behind Schedule: The additive inverse of {[(Progress Schedule Percent/100)*Bid Amount] - (Estimate to Date + Fuel Adjustments to date)} divided by (Contract Bid Amount + Over/Underrun Amount). Then multiply that number by 100.
- Percent Ahead/Behind Time: The additive inverse of (Elapsed Time Percent - Completion Percent) from Review Contract Details Status tab.